A slab table formwork quote is easier to compare when you know how much concrete slab the equipment will actually serve. A set that moves through twelve similar floors spreads its cost over more work than the same set on eight floors. Crane waiting time, irregular slab edges and temporary support can also change the cost of the package.
Add the equipment purchase or rental cost, freight, initial assembly, handling, labour and expected repairs for the same scope and project period. For purchased equipment, subtract a residual value only if you have a reasonable basis for it. Divide the result by the total slab area the quoted equipment is expected to serve. Use the same area definition for every quote and state how you have treated areas formed with separate infill.
Illustrative scenario | Total assumed cost | Area served | Cost per m² poured |
|---|---|---|---|
Planned repeat floors | $48,000 | 12,000 m² | $4.00 |
Fewer repeat floors | $48,000 | 8,000 m² | $6.00 |
Fewer floors plus $4,000 in additional handling | $52,000 | 8,000 m² | $6.50 |
These figures illustrate the calculation. Replace them with your project's costs and expected area.
Ask for the number of tables, their planned moves per floor, and the handling equipment included in the quote. Review slab edges, shafts and non-typical floors separately so you can price the extra infill and labour. Confirm which props or shoring components are in the supply scope and align the estimate with your project team's approved temporary works plan.
Once you have a baseline, test it against fewer repeat floors or higher crane costs. If the preferred quote changes under those assumptions, ask the supplier to clarify which factors drive its estimate.
Send ZEEMO FORM your typical floor plan, slab thicknesses, number of repeat floors, and planned crane access. We can prepare a formwork layout proposal based on your drawings. Use Inquire on the ZEEMO concrete slab table formwork page.